Removal of existing lawn or soil. 

 

Soil is dug out to a depth between 2/3 inches,depending on the current drainage. 

 

A chosen edging is installed to the perimeter to allow a firm fixing for the hardcore base and security of the grass. 

 

A textile weed fabric is pinned down to support the sub base soil, and to prevent weed seedlings. 

 

Installing a hardcore base to the area, and screened with a sand based finish for compacting. 

 

The chosen grass is rolled out and fixed securely. The grass is recommended to be laid with the pile facing into the building for a more aesthetic look. 

 

The grass will then be power brushed or blown to encourage the pile to acclimatise. 

 